A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

What's 5 divided by x squared explain
What's 5 divided by x squared explain
Forget the motor When im on the boat Think of the best time To buy a new coat What am I......?
What were the contributions of the Harappan civilization?
find the sum. write each mixed number in simplest form 4 7/8 + 5 1/4
What's 5 divided by x squared explain
Thelma spent 1/6 of her weekly allowance on dog toys.  1/4 on a dog collar and 1/3 on dog food.  What fraction of her weekly allowance is left
Forget the motor When im on the boat Think of the best time To buy a new coat What am I......?
The ______ was established in 1943 to assist in the transition from a peacetime to a wartime economy ?
josh wanted to buy a bicycle but didn't have enough money. After josh told his troubles to sam slick, sam said,"I can fix that. see that fence? each time you ju