raazshah661 raazshah661
  • 03-09-2020
  • Mathematics
contestada

A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

Which one of the following choices is a known factor that influences flexibility? a. Race and ethnicity b. Body composition c. Degree of self-confidence d.
Find the volume of a rectangular prism if the length is 3x2, the width is 2x, and the height is x2 + 3x + 5. Use the formula V = l ⋅ w ⋅ h, where l is length, w
Who says the following in Macbeth? "Whence is that knocking? How is't with me, when every noise appals me? What hands are here?" A. Duncan B. Macbeth C. Ba
48 is 60% of what number
Write the equation that shows how ADP is changed into ATP?
What is 46% of 22? Use a fraction and express your answer in simplest form
What happens to an enzyme’s structure as it exceeds the typical human body temperature?
What is 1 1/4 plus 2 2/4?
The Intolerable Acts caused the formation of the Continental Navy
What makes you feel empowered in the workplace?