When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

What is the most common cause of iron deficiency anemia?
Who was the 11th president of The United States Of America?
In ΔABC, m∠CAB = 60° and AD is an angle bisector with D ∈BC and AD = 8 ft. Find the distances from D to the sides of the triangle.
what are the types of sentences???
Which issue did not cause arguments at the Constitutional Convention? A. small states vs. large states B. monarchy vs. representative government
Prior to the 18th century, people who exhibited abnormal behavior were thought to be
(a) identify the group in pyridoxal phosphate (plp) that covalently binds enzyme and substrate.
4x+5x-20 = 9x-20 has one , none , or infinite solutions explain.
How do u do this? HELPPPPPPPPPPPPPPPPP
Determine whether the sides given would form an acute, obtuse, or right triangle. 7, 7, 13