If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

Which city did Muhammad return to and declare the holiest city in Islam?
80% of what number is 94
If your goal is to find a mentor who can help encourage you, which category would it fall into?
how to write 2000 using exponents
Which of the following is an extinct group of mollusks related to today's chambered nautilus? a. trilobites b. ammonites c. foraminifera d. stromatolites
Hook was the first to discover cells in a cork. true or false?
Solve 3x-1=10 A) 3 B) 11/3 C) 3/11
Sarah is twice as old as her youngest brother. If the difference Between their ages is 15 years. How old is the youngest brother
what do you call the curved, upper surface of water that commonly appears when using a graduated cylinder?. Describe what causes this?.
There are ________ of muscles that are responsible for chewing movements or mastication. A. Two pairs B. Three pairs C. Four pairs D. Five pairs